I’ve been busy and not too much was happening on the house so I got a little behind on photos
24 (Tuesday)
![]() |
From land |
Roofing stabilizing the second side of the garage trusses.
![]() |
From land |
Piping for utilities from the street.
![]() |
From land |
Open web joists for the floor.
25 (wednesday)
![]() |
From land |
Cleaned up the OSB on the garage.
![]() |
From land |
Utility trench dug and filled.
26 & 27 Nothing happened because we were waiting for the panels.
28 (today)
![]() |
From land |
Panels arrived.
![]() |
From land |
Main house wall starting to go up.
Let us know what you think