Making some progress on the hangar. By beginning of September, the foundation was in and most of the site prep was done. We knew the utility lines to the house would be going straight through the hangar foundation. The one unexpected hiccup, was we had lots of loam on our property, and not so much sand or gravel. So they dug a deep hole, extracted sand and gravel from it, and then buried the tree stumps from land clearing.
To learn more, read the full build story.
Photos from second half of August
- Jerry picking the floor height -- Comments (0)
- Foundation excavation. -- Comments (0)
- Pouring the footings -- Comments (0)
- Footings curing -- Comments (0)
- Forms for the foundation -- Comments (0)
More ...
- Installing insulation on the foundation -- Comments (0)
- Fully insulated foundation interior -- Comments (0)
- Burying stumps -- Comments (0)
- Big hole to get more fill -- Comments (0)
- fill from the stump hole -- Comments (0)
- backfilled and compacted under the slab -- Comments (0)
... Collapse